Projects

BUILDING L1 LUBRIZOL

ROUEN (76)

Industry

Client : Lubrizol
Manager project : ATAUB Architectes
Realization: en étude
Floor area: 659 m²
Mission :  Base + quantités
Cost excluding tax : 2 700 K€ HT

BUILDING DC8 PROLOGIS

SAINT YGOR D'YMONVILLE (76)

Industry

Owner : Prologis France
Project manager : ATAUB Architectes
Realization : In progress
Area : 27 114m²
Mission : Conception + PC
Cost excluding tax : NC

CNPE PENLY LABORATORY

PENLY PETIT CAUX (76)

Industry

Owner : EDF
Project manager : ATAUB Architectes
Realization : In progress
Floor area : 1 976 m² (1 570m² renovated & 1  980m² new)
Mission : Base + EXE
Cost excluding tax : 5 985 K€ HT

BUILDING DC9/DC10 PROLOGIS

SANDOUVILLE (76)

Industry

Owner : Prologis France
Project manager : ATAUB Architectes
Realization : In study
Area : 122 662 m²
Mission : Conception & PC
Cost excluding tax : NC

PLASTIC ENERGY RECYCLING UNIT

PORT JEROME SUR SEINE (76)

Industry

Owner : Plastic Energy
Project manager : ATAUB Architectes
Realization : En étude
Area: 8 537 m²
Mission : Conception + PC
Cost excluding tax : NC

HOUSING LES PASSERELLES

VILLEURBANNE (69)

Housing

Client : Pitch
Project manager : ATAUB Architectes
Realization : livré en 2017
Floor Area: 2 702 m²
Technical performance : RT 2012 Effinergie +
Cost excluding taxe : 3 894 K€ HT

SCHOOL GROUP NERARD

LYON (69)

Education

Maitre d’ouvrage : Ville de Lyon
Maitre d’œuvre : ATAUB Architectes
Réalisation : En cours de chantier
Mission : Complète
Coût HT : 5 200 K€ HT

HOUSING JARDINS HONNA FLOW

HONFLEUR (14)

Housing

Client : Icade
Project manager : ATAUB Architectes
Realization : In study
Floor Area : 2 542 m²
Mission : DET + OPC
Cost excluding tax : 3 957 K€ HT

PKB FACTORY EXTENSION AND RENOVATION

ANGERVILLE LA CAMPAGNE (27)

Industry

Owner : PKB
Project Manager : ATAUB Architectes
realization : En chantier
Floor Area : 7 009 m²
Mission : Base + quantities + EXE
Cost excluding tax : NC

HOTELS AND CINEMA ODYSSEE

VERNON (27)

Urban amenities

Owner : Odyssee immobilier / EAD
project manager : ATAUB Architectes
Realization : In study (PC)
Mission : Base
Cost excluding Taxe : 10 000 K€ HT

BOARDING SCHOOLS KERICHEN

Brest (29)

Education

Client : Brittany Region – SEM Breizh
Project manager : BBGO representative, ATAUB Architects and ENO Architects associates
Achievement : Winner of the February 2020 competition – Work in progress
Usable area : 10 579m²

Mission : Base + Quantities
Cost excluding tax : 18 846 000 € HT

CARMIN RESIDENCE

LE HAVRE (76)

Housing

Client : SOGEPROM
Project manager : ATAUB Architectes
Realization : En cours d’étude
Floor area : 1 875 m²
Mission : Base + qtés + OPC
Cost excluding tax : 3 507 K€ HT

HOUSING RESIDENCE LA VIGIE

HONFLEUR (14)

Housing

Client : BECI Groupe
Project manager : ATAUB Architectes
Realization : En cours d’étude
Floor area : 3 043 m²
Mission : Base + Quantité + OPC
Cost excluding tax : 4 000 K€ HT

SCHOOL CANTEEN JEAN ZAY

LE PETIT QUEVILLY (76)

Education

Client : Ville de Grand Quevilly
Project manager : ATAUB Architectes
Realization : En appel d’offres
SHON : 1 442 m²
Mission : Base + OPC +SSI
Coast excluding tax : 3 663 K€ 

ARNAUD BELTRAME MIDDLE SCHOOL

LUCON (85)

Education

Client : Department of Vendée
Project manager : ATAUB architects / GDV architects associate
Achievement: Winner of the March 2020 competition. Work in progress 
Floor area: 8 493m²

Mission : EXE fluids et structurr + OPC
Cost excluding : 12 500 K € 

HIGH SCHOOL E.MOUNIER GRENOBLE

Grenoble (38)

Education

CONCERTED DEVELOPMENT AREA

CREIL (60)

Urban Planning

Client : SAO – VILLE DE CREIL
Architects : ATAUB Architectes
Landscaper : Espace libre / Miscellaneous network roads : BERIM / Port facilities : Valétudes / Pollution : EACM / Environment : AREA
Achievement : Study in Progress
Cost Excluding taxes : 13 000 000 €

TERTIARY CENTER

VERNON (27)

Offices

Client : SYSNAV
Architects : ATAUB Architectes
Delivery : En cours d’étude
Area : 1 687 sqm
Mission : Based + Quantity
Cost excluding taxes : 1 900 000 €

GOBLINS REHABILITATION

LE HAVRE (76)

Housing

Client: CREDIT AGRICOLE – CAP HORN
Architects : ATAUB Architectes
Delivery :  Lauréat du concours Décembre 2019
Area : 2 610 sqm
Missions: Based + Quantity

EMERGENCY DEPARTMENT

ST LÔ (50)

Health

Client : CENTRE HOSPITALIER MEMORIAL
Architects : ATAUB Architectes, mandataire
Delivery : Winner of the competition 2020 january – study in progress
Area : 2 018 sqm
Mission : Based + Quantity
Cost excluding taxes : 3 200 000 €

BANK HEAD OFFICE

CAMEROUN

International

Client : Bank of central african states
Architects : ATAUB Architectes
Delivery : Winner of the competition – Study in progress
Mission: Based + Quantity

HOUSE OF HEALTH

Le Havre (76)

Health

Client : Groupe DUVAL
Architects : ATAUB Architectes
Delivery :Winner of the competition
Area: 3 500 sqm tertiary activities/1 300 sqm rental housing/1 180 sqm car park

Mission : Based + Quantity
Cost taxe free : NC

VEUVE CLICQUOT OPERATION

SAINT THIERRY (51)

Industry

Client : MHCS
Architects : ATAUB Architects
Delivery : Winner of the competition December 2018
Area : 1 515 sqm

Mission : Based + Quantity
Cost free taxe : € 3 227 760

HOTEL & DWELLINGS

Rouen (76)

Urban amenities

Client : CAP HORN
Architects : ATAUB Architects
Delivery : Study in progress
Area : housing :  5 171 sqm – Senior Residence : 6 755 sqm – Hotel : 7 000 sqm

Mission : Based

HABITAT 76 HEAD OFFICE

Rouen (76)

Offices

Client : HABITAT 76
Architect : ATAUB Architects
Delivery : Finalist 2018 competition
SDP: 3,264 sqm
M
ission : Base + Quantity
Cost free : taxe: Housing: € 5,699,000 – Headquarters: € 9,654,000 – Parking: € 2,052,000

SCHOOL COMPLEX S.SASAKI

LE PETIT QUEVILLY (76)

Education

Client :Petit-Quevilly
Architects : ATAUB Architectes
Delivery :Lauréat du concours Octobre 2019
Area : 4 234 sqm
Mission: Based+ Quantity
Cost excluding taxes : 5 300 K€

EMERGENCY DEPARTMENT

LISIEUX (14)

Health

Client : NORMANDIE CENTRE – GROUPEMENT HOSPITALIER DE TERRITOIRE
Architects : ATAUB Architectes
Delivery : Winner of the competition 2020 – Study in Progress
Area : 2 050 sqm
Mission : Based+ Quantity
Cost excluding taxes : 2 700 K€

COUNTER TERRORISM ACADEMY – ABIDJAN

COTE D'IVOIRE

International

Architects : ATAUB Architectes
Delivery : Study in progress + Under construction
Area : 11 000 sqm
Mission : Based
Cost excluding taxes :18 000 K€ firm slice / 40 000 K€ conditional tranche

DWELLINGS HAIE STREET

BOIS-GUILLAUME (76)

Housing

Client : ATOME
Architects: ATAUB Architectes
Delivery : Study in progress
Area: 1 914 sqm
Mission: Based+ Quantity

FIDUCIARY PRINTER

VIC LE COMTE (63)

Industry

Client : BANQUE DE FRANCE
Mandatory architects : NOX INGENIERIE
Architects : ATAUB Architects
Delivery : Study in progress
Area : Printing 26,000 m² including 3,900 m² of offices
Mission : Based + Process

Cost taxe free : 120 000 000 €

OCCUPATIONAL HOME FOR ADULTS

Graye-sur-Mer (14)

Health

Architects : ATAUB Architects
Delivery :  Delivery 2020/2021
Area : 3 988 sqm
Mission : Based + OPC + BIM
Cost taxe free : € 6,850,285

EXTENSION & REHABILITATION HEAD OFFICE

Rouen (76)

Offices

Client : LUBRIZOL
Architects : ATAUB Architects
Delivery : En cours d’étude
Area : 4 423 sqm
Mission : Based
Cost free taxe : € 7,371,500

URBAN DEVELOPMENT ZONE

PETIT-QUEVILLY (76)

Urban Planning

Client : PETIT-QUEVILLY town
Architects : ATAUB Architectes / SOGETI INGENIERIE  / ESPACE LIBRE : landscaper
Delivery : 2020
Périmètre : 45 Ha
Area : 42 000 sqm

Olympic swimming pool and sports center

CAMEROUN

International

Client : SPORTS MINISTER
Architects: ATAUB Architectes
Delivery : Study in progress
Area : swimming pool 6 000 sqm/ Sports centre : 4 000 sqm
Mission : Based+ Quantity
Cost excluding taxes : 20 000 K€

MEDIA LIBRARY ST VALÉRY EN CAUX

Saint Valéry en caux (76)

Urban amenities

Client : Ville de Saint Valéry en Caux
Architects :  Atelier Module JM CREVEL / Integration of JM CREVEL at ATAUB from 01/04/2017
Delivery : 2018

Area : 870 sqm
Mission : Based + Quantity + OPC
Cost taxe free : € 560,000

STUDENT HOUSING

LE HAVRE (76)

Housing

Client : VINCI IMMOBILIER
Architects : ATAUB Architectes
Delivery : Study in progress
Area : 5 592 sqm
Mission : Based + Quantiy
Cost excluding taxes : 7 000 000€ HT

JEAN CHARCOT MIDDLE SCHOOL

Oissel (76)

Education

Client : Département de la Seine Maritime
Architects : ATAUB Architectes
Delivery : Winner of the competition / 1st phase: Delivery 2018 / 2nd phase: housing units starting construction site 2019
Area : 6 166 sqm (1st phase)

Mission : EXE complète + OPC
Cost taxe free : € 11,495,000

DEPARTMENT HOTEL

Caen (14)

Offices

Client : Conseil Général du Calvados
Architect : ATAUB Architects
Delivery : Winner of the contest on sketch 2013/ Start-up at the end of 2017: delivery planned 2019
Area : 5 062 sqm

Mission : Based + EXE + OPC + BIM
Cost taxe free : € 8,292,500

BANKING AGENCY

Congo

International

Client : Bank of Central African States
Architects :  ATAUB Architects

Delivery : under construction
Area : 6 375 sqm

Mission : Based
Cost taxe free : NC

 

RESIDENCE SERVICES SENIORS

VERNON (27)

Urban amenities

Client: VILLE DE VERNON
Architects : ATAUB Architectes
Delivery : Study in progress
Area : 7 000 sqm
Mission : Based + Quantity
Cost excluding taxes : 10 500 000 €

DEVELOPMENT SPACE

MALAUNAY (76)

Industry

Client : NUTRISET
Architect : ATAUB Architectes, mandataire
Delivery : Under construction
Area : 1 220 sqm
Mission : Based + Quantity
Cost excluding taxes : 1 534 000 €

ESTABLISHMENT FOR ELDERY PERSONS DEPENDANT

VERNEUIL D'AVRE ET D'ITON (27)

Health

Client : CENTRE HOSPITALIER VERNEUIL SUR AVRE
Architects : ATAUB Architectes
Delivery : Winner of the competition 2018 – Study in progress
Area : 9 927 sqm
Mission : Based
Cost excluding taxes : 9 307 000 €

DYNAMIC MUSEUM

Pont l'Evèque (14)

Urban amenities

Client : SPIRIT France
Architects : ATAUB Architects
Scenographer : SARNER
Delivery : Delivery March 2018
Area : 2 911 sqm + 2 276 sqm of car park

Mission : Based + Quantity
Cost taxe free : € 3,042,724

EMERGENCY SERVICE

Clamart (92)

Health

Maître d’ouvrage : Ministère de la Défense
Maître d’œuvre : ATAUB Architectes
Réalisation :  Etude en cours
SDP : 2 300 m²
Mission : Base + Quantités
Coût HT : 7 122 000 €

PENITENCIAL CENTER

Cote d'Ivoire

International

Client : Ministry of Justice and Human Rights
Architects : ATAUB Architects

Delivery : In the course of construction
Area : 7 396 sqm

Mission : Design and direction of execution
Cost taxe taxe : € 11,000,000

PRODUCTION UNITS

Val de Reuil (27)

Industry

Client : JOHNSON and JOHNSON
Architects : ATAUB Architectes, mandataire
Delivery : 2018
Area : 2 539 m²
Mission : Based + Quantity
Cost excluding taxes : € 4,500,000

VIEUX MARCHE PARKING

Rouen (76)

Urban amenities

Client : Rouen Normandie Stationnement
Architects : ATAUB Architects
Delivery : Delivery end of 2018
Area : € 9,791.61 sqm

Mission : Based + Quantity
Cost taxe free : € 2,245,133

V1 BLOCK ZAC QUEVILLY

Le Petit Quevilly (76)

Housing

Client : LOGEAL
Architects : ATAUB Architects
Delivery : Study in progress
Area : 3 100 sqm

Mission : Based
Cost taxe free : € 4,200,000

TERRITORIAL PUBLIC SERVICE CENTER

Isneauville (76)

Offices

Client : Centre de Gestion de la Seine Maritime
Architect : ATAUB Architects
Delivery : Winner of the competition – delivery 2019
Area : 2 957 sqm
Mission : Based + SSI
Cost free taxe : € 5,750,000

HEAD OFFICE MENICON

Villepinte (93)

Offices

Client : LINK CITY
Architects : ATAUB Architects
Delivery : Livraison janvier 2018
Area : 3 597 sqm
Mission : Based + Quantity
Coût HT : € 5,300,000

COURTS OF APPEAL

Cote d'Ivoire

International

Client : Ministry of Justice and Human Rights
Architects : ATAUB Architects
Delivery : In the course of construction
Mission : Design and direction of execution
Cost taxe free : € 8,700,000

PRODUCTION UNITS PLANET PHARMA

Le Petit Quevilly (76)

Industry

Client : PLANET PHARMA
Architects : ATAUB Architects
Delivery : 2018
Area : 3 000 sqm
Mission : Based + Quantity
Cost taxe free : € 5,800,000 – € 9,000,000 € with process

FRENCH BLOOD ESTABLISHMENT

Rennes (35)

Health

Client : EFS Bretagne
Architects : ATAUB Architects
Delivery :  Study in progress
Area : 2 300 sqm
Mission : Based
Cost taxe free : € 3,191,958

V8 BLOCK

Petit Quevilly (76)

Housing

52 HOUSING IN 4 LEVELS

Client : VINCI IMMOBILIER NORD EST
Architects : ATAUB Architects
Delivery : study in progress
Area : 3034,08 sqm
Missions : Based + OPC
Cost free taxe : € 3 787 000

BUILDING RESTORATION

Verneuil-sur-Avre (27)

Education

Client : Ecole des Roches
Architects : ATAUB Architects
Delivery: delivered in July 2018
Area : 1 387 sqm
Cost taxe free : € 3,800,000
Mission : Based + DET + VISA + OPC
Capacity : 400 meals

YOUTH AND SPORT POLE

Le Havre (76)

Urban amenities

Client : Ville du Havre
Architects : ATAUB Architects
Delivery : 2013
Area: 2 210 sqm
Mission : Based + OPC + SSI
Cost taxe free : € 3,385,000

NATIONAL INSTITUTE OF JUDICIAL TRAINING

Cote d'Ivoire

International

Maître d’ouvrage : Ministère de la Justice et des Droits de l’Homme
Maître d’œuvre : ATAUB Architectes
Réalisation : en cours de chantier
SHON : 12 142 m² dont hébergements 3 622 m²
Mission : Conception et direction de l’exécution
Coût HT : 12 600 000 €

“LIGHT HOUSE” WOODEN TOWER

LE HAVRE (76)

Housing

Client : EIFFAGE IMMOBILIER
Architect : ATAUB Architectes
Delivery : Study in progress
Area : 4 374 m²
Mission : Base
Coût HT : 10 000 000 €

ANIMAL FACILITY PASTEUR INSTITUT

LILLE (59)

Industry

Client : INSTITUT PASTEUR
Architect : ATAUB Architectes, mandataire
Delivery : Under construction
Area : 2 000 sqm
Mission : Based
Cost excluding taxes : 3 500 000 €

COLLEGE VAL DE SEINE GYMNASIUM

Grand Quevilly (76)

Urban amenities

Client : Région Haute Normandie
Architects : ATAUB Architects
Delivery : Delivery 2013
Area : 1 950 sqm
Mission : Based + EXE + OPC
Cost taxe free : € 3,434,000

POLYVALENT COLLEGE AIME CESAIRE

Clisson (44)

Education

Client : Conseil Régional Pays de Loire
Architects : ATAUB Proxy Architects, LINEA associate
Delivery : Winner of the competition 2010, Delivered in 2013 / Extension 2018
Area : 19 500 sqm + Extension : 438 sqm

Cost taxe free : € 30,640,000 + Extension : € 1,800,000
Mission : Based + Quantity + SSI

FIDUCIARY CENTER

SAINGHIN-EN-MELANTOIS (59)

Industry

Client : BANQUE DE FRANCE
Architect : ATAUB Architectes
Delivery : 2016
Area : 5 150 sqm
Cost excluding taxes : Building 24 000 000 € / logistic process : 4 900 000 €

CHURCHILL BOULEVARD

Le Havre (76)

Housing

Client : HABITAT 76
Architects : ATAUB Architects
Delivery : Winner of the competition in 2016 – In progress – Delivery 1st tranche August 2018
Area : 8 420 sqm

Mission : Competitive Dialogue – Base + Synthesis + BIM
Cost taxe free: € 10,893,000

CHARLEMAGNE COLLEGE

Congo

Education

Client : French Lycee Charlemagne – AEFE
Architects : ATAUB architects Representative – ATAUB AFRIQUE associe
Delivery : Winner of the competition in 2014
Delivery: 1st phase in 2017 – 2nd phase under construction
Area : 8 725 sqm

Mission : Based + Quantity + SSI
Cost taxe free : €7,795,000

UNIVERSITY HOSPITAL CENTER

Rouen (76)

Health

Client : CHU Hôpitaux de Rouen
Architects : Michel Beauvais Attorney Architect / ATAUB Associated Architects
Réalisation : Winner of the competition September 2015 / Under construction
Area : 28 000 sqm

Mission : Based + EXE
Cost taxe free : € 60,440,000

REUNIFICATION STADIUM

Cameroon

International

Maitre d’ouvrage : MINMAP – MINSEP
Maitre d’œuvre : ATAUB Architectes
Réalisation : En cours de chantier, Livraison 2019
SHON : 10 000 m²
Mission : Base
Coût HT : 50 000 000 €

LABORATORIES AND OFFICES

VERNEUIL EN HALATTE (60)

Industry

Client : INERIS
Architect : ATAUB Architectes
Delivery : 2016 March
Area : 4 000 sqm
Missions : Based + Syntesis
Cost excluding taxes : 8 000 000 €

PRIVATE CLINIC

Bois-Guillaume

Health

Client : Clinique du Cèdre
Architects : ATAUB Architects
Delivery :  2018
Area : 4 000 sqm
Mission : Based + OPC + CSSI
ost taxe free : € 5,450,000

GENESIS LABORATORY

Saint Etienne du Rouvray (76)

Industry

Client : Université de Rouen
Architects : ATAUB Architects
Delivery : Delivery 2015
Area : 410 sqm
Mission : Based + EXE
Cost taxe free : € 1,950,000

ELECTRONIC PRODUCTION UNITS

Val de Reuil (27)

Industry

Client : SCI de l’Orée 20133
Architects : ATAUB Architects
Delivery : Delivered in December 2014
Area : 5 400 sqm

Mission : Based + Quantity
Cost taxe free : € 3,060,000

TERTIARY CENTER ODYSSEE

GABON

International

Client : ACCINCO/OGAR
Architects : ATAUB Architectes
Delivery : 2019 September
Area : 6 000 sqm
Mission: Based
Cost excluding taxes : 15 000 K€

ORLÉANS FACULTY

Orléans (45)

Education

Client : Département du Loiret
Architects : ATAUB Architectes
Delivery : Lauréat du concours 2011 / Livraison fin 2015
Area : 5 966 sqm
Mission : Based + SSI + SIGN
Cost taxe free : € 11,000,000

BLAST PROOF CONTROL ROOMS

Le Havre (76)

Industry

Client : CHEVRON Oronite SAS
Architects : ATAUB Architects
Delivery : Delivery December 2014
Area : 900 sqm

Mission : Base + Quantities + OPC (permanent) + furniture ergonomics mission
Cost taxe free : € 3,900,000

REHABILITATION JACQUES CARTIER

Le Havre (76)

Housing

Client : LOGEO Seine Estuaire
Architects: ATAUB Architectes
Delivery : Under construction
Mission: Based + Quantity
Cost excluding taxes : 8 200 000 €

HOSPITAL CENTER

Saint Aubin lès Elbeuf (76)

Health

Client : Centre Hospitalier Intercommunal Elbeuf Louviers Val de Reuil
Architects : ATAUB Architects
Delivery : November 2015 Delivery / Pediatric Emergencies Extension October 2018
Area : 14 640 sqm / Pediatric emergencies 525 sqm

Mission : Basd
Cost taxe free : € 22,000,000  / Pediatric emergencies € 1,500,000

BANKING AGENCY BEAC

Equatorial Guinea

International

Maitre d’ouvrage : Banque des Etats d’Afrique Centrale
Maitre d’œuvre : ATAUB Architectes
Réalisation : Livraison 2018
Surface : 7 240 m²

TELTOW DISTRICT

GONFREVILLE L'ORCHER (76)

Housing

Client : CARRERE (+ LOGEO Seine Estuaire)
Architects : ATAUB Architectes
Delivery : Under construction
Area : 3 000 sqm shops /  5 200 sqm dwellings / 4 500 dsm basement parking / 10 000 sqm public areas
Mission: Based + Quantity
Cost excluding taxes : 9 700 000 €

BGFI BANK HEAD OFFICE

Congo

International

Client : BGFI
Architects : ATAUB Mandatory Architects
Delivery : 2016
Area : 4 969 sqm
Mission : Based + OPC
Cost taxe free : € 10,061,600

ALTIX ASSEMBLY WORKSHOP

Val de Reuil (27)

Industry

Client : ALTIX
Architects : ATAUB Architects
Delivery : 2012
Area : 2 190 m²
Mission : Based + Quantity
Cost taxe free: € 1,686,000

HOUSING COMPLEX DUGUAY TROUIN

Le Havre (76)

Housing

Client : CIF / PFN
Architects : ATAUB Architects
Delivery : Delivery March 2018
Area : 2 873 sqm

Mission : Based + Quantity
Cost taxe free : € 3,510,000 (off road)
Environmental performance: RT 2012

 

SCHOOL COMPLEX NELSON MANDELA

Saint Herblain (44)

Education

Client : Mairie de Saint Herblain
Architects : LinéA architects – ATAUB Associated Architects
Delivery  : Winner of the competition, Delivered in 2015
Area : 5 245 msqm

Mission : Based + Étendue
Cost taxe free : € 8,290,000
Energy performance: 60% higher than BBC criteria
Green roofs, solar panels for domestic hot water production, insulation from the outside, natural light.

EUROPE CLINIC

Rouen (76)

Health

Client : Clinique de l’Europe
Architects : ATAUB Architects
Delivery : Delivery 2016
Area : 2 788 sqm
Mission : Based + Quantity
Cost taxe free : € 4,000,000

SPACE TRAY

VERNON (27)

Urban Planning

Client : SPL PLATEAU DE L’ESPACE
Architects : ATAUB Architectes
Delivery : Study in progress
Area : 70 Ha
Cost excluding taxes : 65 M€

BANK HEAD OFFICE BEAC

Equatorial Guinea

International

Client : Bank of Central African States
Architects : ATAUB Architectes mandataire
Delivery : April 2013
Area : 18 000 sqm
Mission : Based + Quantity
Cost taxe free : NC

POLYVALENT COLLEGE ANGUIER

Eu (76)

Education

Client : Conseil Régional de la Haute Normandie
Architects :  ATAUB architects Representative
Delivery : Winner of the competition in 2006 – Delivered in 2010 and 2011
Area : 21 000 sqm new – 7 000 sqm rehabilitation (workshops and classrooms)
Mission : Bases + Exécution

Cost taxe free :  € 34,000,000
HQE performance: Insulation from the outside, wood boiler, double skin concrete, vertical sunshade. Work done in occupied site.

VALMY DOMAIN

Le Havre (76)

Housing

Client : PFN
Architects : ATAUB Architects
Delivery : 2016
Mission : Based + Quantity
Area : 5 177 sqm
Cost taxe free : € 8,000,000

 

AIRPORT DISTRICT

TCHAD

Urban Planning

Client : Banque Africaine de Développement
Architects : ATAUB Architectes
Delivery : 2013 March
Perimeter right-of-way : 14,7 Ha
Area : 264 790 m²

HEAD OFFICE & ECO-NEIGHBORHOOD HOUSING

Rouen (76)

Offices


Client : ADIM – MATMUT
Architects : ATAUB Architects
Delivery : Winner of the contest – Delivery 2017
Area : Offices 4 720 sqm/ 44 housing 3 310 sqm/ shop 163 sqm
Mission : Based
Cost free taxe : € 14,437,000

TERTIARY CENTER

Isneauville (76)

Offices

Client : CAP HORN / SCCV VICTORIA
Architects : ATAUB Architectes
Delivery : 2012 / 2014
Area : 2 930 sqm – 5 860 sqm
Mission : Based + Quantity
Cost excluding taxes : 2 720 310 € – 3 304 358 €

 

 

HEAD OFFICE SOGETI

BOIS-GUILLAUME (76)

Offices

Client : SOGETI
Architects : ATAUB Architectes
Delivery : 2012
Area : 605 sqm
Mission : Based + Quantity
Cost excluding taxes : 1 062 000 €

SPORTS COMPLEX

Clisson (44)

Urban amenities

Client : Conseil Régional Pays de Loire
Architects : ATAUB Mandatory Architects
Delivery :  2013

Area : 2 000 sqm
Mission : Based + Quantity + SSI
Cost taxe free : € 2,600,000

 

SHOPPING CENTER

Mers les Bains (80)

Urban amenities

Client : SNC MERS DEVELOPPEMENT & CIE
Architects : ATAUB Architects
Delivery :  2011
Cost taxe free : 5 493 079 €

TERTIARY CENTER – ZAC RONCE

ISNEAUVILLE (76)

Offices

Client : CAP HORN / SAS MAGELLAN  2
Architects : ATAUB Architectes
Delivery : 2012 – Winner of the competition 2008
Area : 6 435 sqm
Mission : Based + Quantity
Cost excluding taxes : 5 339 869 €

HOSPITAL CENTER

Verneuil d'Avre et d'Iton (27)

Health

Client : Centre hospitalier de Verneuil sur Avre
Architects : ATAUB Architects
Delivery : Nurcing homes 2011 / Hospital Center 2012 / Extension hospital center under study Winner of the competition 2018
Area : Nurcing homes 5 530 sqm / Hospital center 8 430 sqm

Mission : Based + EXE
Cost taxe free : Nurcing homes : € 10,185,000 € /  Hospital Center : €9,594,000

 

NURSING HOME VERNOLINE

VERNEUIL D'AVRE ET D'ITON (27)

Health

Client : Centre hospitalier de Verneuil sur Avre
Architect : ATAUB Architectes
Delivery : 2011
Area : 8 430 sqm
Mission : Based + execution
Cost excluding taxes : 10 185 000 €

TERTIARY CENTER TOTAL

GONFREVILLE L'ORCHER (76)

Offices

Client : TOTAL
Architects : ATAUB architectes
Delivery: 2006
AREA : 5 455 sqm + 1 760 sqm
Mission : Based + Quantity
Cost excluding taxes : 12 500 K€